Previous Migration Sprint


Migration Sprint 4

Sprint 4 execution started on Wednesday 5 August 2026 and ran until Tuesday 6 October 2026. 

cycle_3.jpg

gantt_chart.jpg

Sprint Planning 

Sprint 4 Planning opened on Wednesday 15 July 2026 and the Sprint 4 Baselined Schedule is available on Kestrel.

All Suppliers were required to submit their weekly granularity forecast plans by Wednesday 22 July 2026, and active Suppliers were required to submit a Combined Schedule (Committed and Forecast).

For dates on the next planning window, please see the Migration Sprints page of this website. 


Sprint Execution 

Sprint 4 execution started on Wednesday 5 August 2026 and closed on Tuesday 6 October 2026.

The Migration Control Centre (MCC) actively monitored migrations during Sprint execution.  

Information on migration processes was shared via Programme governance.  

execution.jpg

retrospective.jpg

Sprint Retrospective 

The Sprint 4 retrospective will be held on Monday 19 October 2026 to reflect on the closed Sprint, celebrate successes, capture lessons learned, and agree improvements for future cycles.

If there are any lessons learned that you would like to be considered for this session, please email the Migration team at Migration@mhhsprogramme.co.uk 


Key Timelines 

  • Wednesday 22 July 2026 - Submission deadline: 
    Deadline for all Suppliers to have submitted their schedules (by the end of the day)
  • Wednesday 29 July 2026 - Sprint 4 baseline published: 
    • Baselined - Committed and forecast schedule released to Suppliers
    • Baselined - Aggregate schedules released
  • Wednesday 5 August 2026 - Sprint 4 Execution started: 
    • Supplier Migrations began, following Baselined committed schedule
  • Tuesday 6 October 2026 – Sprint 4 Execution ended
calendar_pages.jpg