Previous Migration Sprint


Migration Sprint 1

Sprint 1 planning is now closed.

Sprint 1 execution began on Wednesday 4 February 2026 and closed on Tuesday 31 March 2026.

cycle_3.jpg

gantt_chart.jpg

Sprint Planning 

Migration Sprint 1 Planning ran from 7-21 January 2026.

For dates on the next planning window, please see the Migration Sprints page of this website

 

 

 


Sprint Execution 

Sprint 1 execution started on Wednesday 4 February 2026 and finished on Tuesday 31 March 2026.

execution.jpg

retrospective.jpg

Sprint Retrospective 

A Sprint 1 retrospective is scheduled for Monday 13 April 2026, to reflect on the closed Sprint, celebrate successes, capture lessons, and agree improvements for future cycles.

We'll publish the Sprint 1 Retrospective materials on the Migration Sprint Retrospectives page of this website.

If you have any questions, please email the Migration team at Migration@mhhsprogramme.co.uk 


Key Timelines 

  • Wednesday 21 January 2026 - Submission deadline: 
    Deadline for all Suppliers to have submitted their schedules (by the end of the day)
  • Wednesday 28 January 2026 - Sprint 1 baseline published: 
    • Baselined - Committed and forecast schedule released to Suppliers
    • Baselined - Aggregate schedules released
  • Wednesday 4 February 2026 - Sprint 1 Execution started: 
    • Supplier Migrations began, following Baselined committed schedule
  • Tuesday 31 March 2026 – Sprint 1 Execution ended