Previous Migration Sprint


Migration Sprint 2

Sprint 2 execution started on Wednesday 1 April 2026 and closed on Tuesday 2 June 2026.

cycle_3.jpg

gantt_chart.jpg

Sprint Planning 

Sprint 2 Planning is now closed.

Migration Sprint 2 Planning opened on Wednesday 11 March 2026.

The Sprint 2 Baselined Schedule was published via Kestrel on Wednesday 25 March 2026.

For dates on the next planning window, please see the Migration Sprints page of this website

 

 

 

 


Sprint Execution 

Sprint 2 execution started on Wednesday 1 April 2026 and ran until Tuesday 2 June 2026.

execution.jpg

retrospective.jpg

Sprint Retrospective 

A Sprint 2 retrospective is scheduled for the end of Sprint 2 execution phase, on Monday 15 June 2026, to reflect on the closed Sprint, celebrate successes, capture lessons learned, and agree improvements for future cycles.

We'll publish the Sprint 2 Retrospective materials on the Migration Sprint Retrospectives page of this website.

If you have any questions, please email the Migration team at Migration@mhhsprogramme.co.uk 


Key Timelines 

  • Wednesday 18 March 2026 - Submission deadline: 
    Deadline for all Suppliers to have submitted their schedules (by the end of the day)
  • Wednesday 25 March 2026 - Sprint 2 baseline published: 
    • Baselined - Committed and forecast schedule released to Suppliers
    • Baselined - Aggregate schedules released
  • Wednesday 1 April 2026 - Sprint 2 Execution started: 
    • Supplier Migrations began, following Baselined committed schedule
  • Tuesday 2 June 2026 – Sprint 2 Execution ended
calendar_pages.jpg