Upcoming Migration Sprint


Migration Sprint 1

The upcoming Sprint is Sprint 1.  

Sprint planning for this cycle is now open with Supplier submissions due on Wednesday 21 January 2026 and the Sprint 1 Baselined Schedule will be published via Kestrel on Wednesday 28 January 2026

After the end of Sprint 1 planning, a Sprint 1 Migration Plan Summary will be shared which provides an overview of the outcomes from the MHHS Sprint 0 planning phase.

Sprint 1 execution begins on Wednesday 4 February 2026.

cycle_3.jpg

gantt_chart.jpg

Sprint Planning 

Migration Sprint 1 Planning runs from Wednesday 7 January to Wednesday 21 January 2026.

All Suppliers are required to submit their weekly granularity forecast plans by Wednesday 21 January 2026, and Sprint 0 and Sprint 1 Suppliers were required to submit a Combined Schedule (Committed and Forecast)​​. 

For dates on the next planning window, please see the Migration Sprints page of this website


Sprint Execution 

Sprint 1 execution starts on Wednesday 4 February 2026 and runs to Tuesday 31 March 2026.

The Migration Control Centre (MCC) will actively monitor migrations during sprint execution.

Information on migration process will be shared via Programme governance.

There is a Microsoft Teams channel to provide updates to Central Parties and active Suppliers. If you think you need access to this, please email Migration@mhhsprogramme.co.uk  

execution.jpg

retrospective.jpg

Sprint Retrospective 

A Sprint 1 retrospective will be held at the end of the Sprint 1 execution phase to reflect on the closed Sprint, celebrate successes, capture lessons, and agree improvements for future cycles.  

If there are any lessons learned that you would like to be considered for this session, please email the Migration team at Migration@mhhsprogramme.co.uk 


Key Timelines 

  • Wednesday 21 January 2026 - Submission deadline:  All Suppliers must submit schedules (by the end of the day) 
  • Wednesday 28 January 2026 - Sprint 1 baseline published:  
    • Baselined - Committed and forecast schedule released to Suppliers 
    • Baselined - Aggregate schedules released 
  • Wednesday 4 February 2026 - Sprint 1 Execution starts:  
    • Supplier Migrations begin, following Baselined committed schedule
  • Tuesday 31 March 2026 – Sprint 1 Execution ends 