Early Life Support
Early Life Support (ELS) Phase 3 Exit
On Thursday 12 February 2026, the Migration & Cutover Advisory Group (MCAG) agreed that the Programme is operating within acceptable parameters to exit ELS.
Thank you to all participants for their continued engagement and commitment to the success of the MHHS Programme.
If you have any questions about the exit of ELS, please email the Operational Readiness team at Opreadiness@mhhsprogramme.co.uk
Early Life Support Model
The Early Life Support (ELS) period focused on the early months of the MHHS migration period, where the Programme monitored the performance of the new systems and processes, in conjunction with Code Bodies and Central Service Providers.
The ELSM set out:
- The enhanced support that was expected to be in place during the ELS period
- The governance approach for the ELS period and roles & responsibilities
- ELS operating phases and exit criteria
- The key Early Life risk areas, monitoring and performance measures
- Risks, assumptions and dependencies
On Tuesday 29 April 2025 the Migration & Cutover Advisory Group (MCAG) approved the baselined version of the Early Life Support Model which you can view below:
MHHS Early Life Support Model v1.0
Elexon Performance Assurance Monitoring during MHHS Migration
This activity is now complete.
If you have any questions, please email the Operational Readiness team at Opreadiness@mhhsprogramme.co.uk