CR055: Amendments to M10 and Corresponding Milestones

On this page you will find the details of Change Request CR055: Amendments to M10 and corresponding Milestones, as well as all related supporting documentation required for the Impact Assessment.  

Due to the nature of this Change Request and the impact it will have on the proposed Programme Plan, and T1 Milestones, CR055 requires Ofgem approval. Therefore, it is important that Impact Assessment feedback provided by Programme participants is comprehensively qualitative and quantitative, providing the right evidence to allow for an informed Ofgem decision. All Impact Assessment submissions will be shared with Ofgem unredacted.  

The Programme has developed additional supporting documentation to assist Programme participants in providing this evidence. This includes: 

CR055 - Amendments to M10 and Corresponding Milestones

M10 Recalibration Overview

CR055 Impact Assessment Supporting Guidance

MHHS Programme Plan v6.0 (Microsoft Project)

MHHS Plan Outline v6.0 (Excel)

MHHS Milestone Register v6.0

As a reminder, you can also reference MHHS process documentation and existing guidance:

MHHS Change Request Form Guidance to Programme participants

MHHS Change Control Approach

MHHS Programme Governance Framework

Programme Planning Dialogue Slides

You can also find a Q&A document from the MHHS Programme Planning Dialogue Session and CR055 webinar below:

Webinar Q&A

The Impact Assessment Window runs from 23 September to 17:00 on 4 October 2024. 

If you have any questions on CR055, please email  PMO@mhhsprogramme.co.uk