M10/M11 Cutover Plan


blue clock

The M10/M11 Cutover Plan sets out the activities that MHHS participants will be required to carry out in the lead up to M10, at M10, and between M10 and M11 to enable the Programme to successfully reach both M10 and M11 respectively. It outlines what these activities are along with when they are expected to take place, who the responsible parties are, the declaration requirements that participants will be expected to follow and the key dependencies that may impact particular activities.   

The updated M10/M11 Cutover Plan was taken to the Migration & Cutover Advisory Group for re-baselining on Tuesday 1 April 2025 and confirmed for approval. You can view the baselined artefacts below:

M10/M11 Cutover Plan v1.1

M10/M11 Cutover Delivery Plan v1.1

M10 Acceptance Criteria v1.1

If you have any questions, please email the Transition & Operational Readiness team at OpReadiness@mhhsprogramme.co.uk