Readiness Assessment 5/6 coming soon!
◆ Published: 09/04/2025
Readiness Assessment 5/6 is a critical input and evidence capturing mechanism to inform and support wider Milestone 10 (M10) readiness tracking activity. It is key in enabling the Programme to identify any risks and issues in advance of Go-Live.
Readiness Assessments 5/6 will focus on:
- M10 (Central Systems ready for migrating Meter Point Administration Numbers (MPANs))
- M11 (Initiation of the migration of MPANs), as well as the pre-requisites for M10
- Input into Control Points 3 and 4 (readiness for start of Migration)
Readiness Assessment 5/6 opens on Monday 28 April 2025.
Participants will have three weeks to complete the assessment and submit their responses to the Programme by 17:00 on Friday 16 May 2025.
For more information about this Readiness Assessment, please visit the Readiness Assessment 5/6 page of this website.
If you have any questions, please email PPC@mhhsprogramme.co.uk